Sikorsky Raider X prototype 90% complete, engine delivery expected in November

by Gillian Rich

The Sikorsky Raider X was 90% complete in June 2022 at the company's West Palm Beach facility. The aircraft is shown here with the turreted cannon under the nose and with the weapons bay door open, with the modular effects launcher attached. (Sikorsky)

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaissance Aircraft (FARA) programme, is 90% complete and the company has 98% of parts on hand for the build.

The company is waiting for the T901-GE-900 Improved Turbine Engine (ITE) from General Electric to arrive in November 2022.

The ITE is “the last significant piece of our helicopter that hasn't been installed”, Pete Germanowski, FARA chief engineer at Sikorsky, told reporters on 28 June.

The army announced on 23 March that it conducted the first ‘light-off' off General Electric's T901 First Engine to Test (FETT), meaning power was produced by igniting fuel in the engine.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/sikorsky-raider-x-prototype-90-complete-engine-delivery-expected-in-november/

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaiss...

Sikorsky Raider X prototype 90% complete, engine delivery expected in November

by Gillian Rich

The Sikorsky Raider X was 90% complete in June 2022 at the company's West Palm Beach facility. The aircraft is shown here with the turreted cannon under the nose and with the weapons bay door open, with the modular effects launcher attached. (Sikorsky)

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaissance Aircraft (FARA) programme, is 90% complete and the company has 98% of parts on hand for the build.

The company is waiting for the T901-GE-900 Improved Turbine Engine (ITE) from General Electric to arrive in November 2022.

The ITE is “the last significant piece of our helicopter that hasn't been installed”, Pete Germanowski, FARA chief engineer at Sikorsky, told reporters on 28 June.

The army announced on 23 March that it conducted the first ‘light-off' off General Electric's T901 First Engine to Test (FETT), meaning power was produced by igniting fuel in the engine.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/sikorsky-raider-x-prototype-90-complete-engine-delivery-expected-in-november/

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaiss...

Sikorsky Raider X prototype 90% complete, engine delivery expected in November

by Gillian Rich

The Sikorsky Raider X was 90% complete in June 2022 at the company's West Palm Beach facility. The aircraft is shown here with the turreted cannon under the nose and with the weapons bay door open, with the modular effects launcher attached. (Sikorsky)

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaissance Aircraft (FARA) programme, is 90% complete and the company has 98% of parts on hand for the build.

The company is waiting for the T901-GE-900 Improved Turbine Engine (ITE) from General Electric to arrive in November 2022.

The ITE is “the last significant piece of our helicopter that hasn't been installed”, Pete Germanowski, FARA chief engineer at Sikorsky, told reporters on 28 June.

The army announced on 23 March that it conducted the first ‘light-off' off General Electric's T901 First Engine to Test (FETT), meaning power was produced by igniting fuel in the engine.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/sikorsky-raider-x-prototype-90-complete-engine-delivery-expected-in-november/

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaiss...

Sikorsky Raider X prototype 90% complete, engine delivery expected in November

by Gillian Rich

The Sikorsky Raider X was 90% complete in June 2022 at the company's West Palm Beach facility. The aircraft is shown here with the turreted cannon under the nose and with the weapons bay door open, with the modular effects launcher attached. (Sikorsky)

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaissance Aircraft (FARA) programme, is 90% complete and the company has 98% of parts on hand for the build.

The company is waiting for the T901-GE-900 Improved Turbine Engine (ITE) from General Electric to arrive in November 2022.

The ITE is “the last significant piece of our helicopter that hasn't been installed”, Pete Germanowski, FARA chief engineer at Sikorsky, told reporters on 28 June.

The army announced on 23 March that it conducted the first ‘light-off' off General Electric's T901 First Engine to Test (FETT), meaning power was produced by igniting fuel in the engine.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/sikorsky-raider-x-prototype-90-complete-engine-delivery-expected-in-november/

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaiss...

Sikorsky Raider X prototype 90% complete, engine delivery expected in November

by Gillian Rich

The Sikorsky Raider X was 90% complete in June 2022 at the company's West Palm Beach facility. The aircraft is shown here with the turreted cannon under the nose and with the weapons bay door open, with the modular effects launcher attached. (Sikorsky)

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaissance Aircraft (FARA) programme, is 90% complete and the company has 98% of parts on hand for the build.

The company is waiting for the T901-GE-900 Improved Turbine Engine (ITE) from General Electric to arrive in November 2022.

The ITE is “the last significant piece of our helicopter that hasn't been installed”, Pete Germanowski, FARA chief engineer at Sikorsky, told reporters on 28 June.

The army announced on 23 March that it conducted the first ‘light-off' off General Electric's T901 First Engine to Test (FETT), meaning power was produced by igniting fuel in the engine.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/sikorsky-raider-x-prototype-90-complete-engine-delivery-expected-in-november/

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaiss...

Sikorsky Raider X prototype 90% complete, engine delivery expected in November

by Gillian Rich

The Sikorsky Raider X was 90% complete in June 2022 at the company's West Palm Beach facility. The aircraft is shown here with the turreted cannon under the nose and with the weapons bay door open, with the modular effects launcher attached. (Sikorsky)

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaissance Aircraft (FARA) programme, is 90% complete and the company has 98% of parts on hand for the build.

The company is waiting for the T901-GE-900 Improved Turbine Engine (ITE) from General Electric to arrive in November 2022.

The ITE is “the last significant piece of our helicopter that hasn't been installed”, Pete Germanowski, FARA chief engineer at Sikorsky, told reporters on 28 June.

The army announced on 23 March that it conducted the first ‘light-off' off General Electric's T901 First Engine to Test (FETT), meaning power was produced by igniting fuel in the engine.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/sikorsky-raider-x-prototype-90-complete-engine-delivery-expected-in-november/

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaiss...

Sikorsky Raider X prototype 90% complete, engine delivery expected in November

by Gillian Rich

The Sikorsky Raider X was 90% complete in June 2022 at the company's West Palm Beach facility. The aircraft is shown here with the turreted cannon under the nose and with the weapons bay door open, with the modular effects launcher attached. (Sikorsky)

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaissance Aircraft (FARA) programme, is 90% complete and the company has 98% of parts on hand for the build.

The company is waiting for the T901-GE-900 Improved Turbine Engine (ITE) from General Electric to arrive in November 2022.

The ITE is “the last significant piece of our helicopter that hasn't been installed”, Pete Germanowski, FARA chief engineer at Sikorsky, told reporters on 28 June.

The army announced on 23 March that it conducted the first ‘light-off' off General Electric's T901 First Engine to Test (FETT), meaning power was produced by igniting fuel in the engine.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/sikorsky-raider-x-prototype-90-complete-engine-delivery-expected-in-november/

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaiss...

Sikorsky Raider X prototype 90% complete, engine delivery expected in November

by Gillian Rich

The Sikorsky Raider X was 90% complete in June 2022 at the company's West Palm Beach facility. The aircraft is shown here with the turreted cannon under the nose and with the weapons bay door open, with the modular effects launcher attached. (Sikorsky)

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaissance Aircraft (FARA) programme, is 90% complete and the company has 98% of parts on hand for the build.

The company is waiting for the T901-GE-900 Improved Turbine Engine (ITE) from General Electric to arrive in November 2022.

The ITE is “the last significant piece of our helicopter that hasn't been installed”, Pete Germanowski, FARA chief engineer at Sikorsky, told reporters on 28 June.

The army announced on 23 March that it conducted the first ‘light-off' off General Electric's T901 First Engine to Test (FETT), meaning power was produced by igniting fuel in the engine.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/sikorsky-raider-x-prototype-90-complete-engine-delivery-expected-in-november/

Sikorsky said that the prototype Raider X, its submission for the US Army's Future Attack Reconnaiss...