UK to reassess Ajax programme

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) Ajax programme after the first batch of production standard armoured fighting vehicles (AFVs) was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

Details of the exercise are still being worked out and the MoD’s chief civilian administrator, Stephen Lovegrove, is preparing to issue a formal notification to the UK parliament’s Public Accounts Committee about the reassessment. These notifications are only made when major cost overruns, technical glitches or programme delays are involved.

The revelation of the reassessment was made by Air Marshal Richard Knighton, Deputy Chief of the Defence Staff for Financial and Military Capability, in evidence to the committee on 28 May.

AM Knighton confirmed the Ajax vehicles made by General Dynamics Land Systems-UK (GDLS-UK) were not ready to be accepted by the British Army as planned last year.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/29cf9003-fcc5-4c72-af61-e7a41a7aa603/

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) ...

UK to reassess Ajax programme

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) Ajax programme after the first batch of production standard armoured fighting vehicles (AFVs) was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

Details of the exercise are still being worked out and the MoD’s chief civilian administrator, Stephen Lovegrove, is preparing to issue a formal notification to the UK parliament’s Public Accounts Committee about the reassessment. These notifications are only made when major cost overruns, technical glitches or programme delays are involved.

The revelation of the reassessment was made by Air Marshal Richard Knighton, Deputy Chief of the Defence Staff for Financial and Military Capability, in evidence to the committee on 28 May.

AM Knighton confirmed the Ajax vehicles made by General Dynamics Land Systems-UK (GDLS-UK) were not ready to be accepted by the British Army as planned last year.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/29cf9003-fcc5-4c72-af61-e7a41a7aa603/

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) ...

UK to reassess Ajax programme

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) Ajax programme after the first batch of production standard armoured fighting vehicles (AFVs) was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

Details of the exercise are still being worked out and the MoD’s chief civilian administrator, Stephen Lovegrove, is preparing to issue a formal notification to the UK parliament’s Public Accounts Committee about the reassessment. These notifications are only made when major cost overruns, technical glitches or programme delays are involved.

The revelation of the reassessment was made by Air Marshal Richard Knighton, Deputy Chief of the Defence Staff for Financial and Military Capability, in evidence to the committee on 28 May.

AM Knighton confirmed the Ajax vehicles made by General Dynamics Land Systems-UK (GDLS-UK) were not ready to be accepted by the British Army as planned last year.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/29cf9003-fcc5-4c72-af61-e7a41a7aa603/

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) ...

UK to reassess Ajax programme

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) Ajax programme after the first batch of production standard armoured fighting vehicles (AFVs) was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

Details of the exercise are still being worked out and the MoD’s chief civilian administrator, Stephen Lovegrove, is preparing to issue a formal notification to the UK parliament’s Public Accounts Committee about the reassessment. These notifications are only made when major cost overruns, technical glitches or programme delays are involved.

The revelation of the reassessment was made by Air Marshal Richard Knighton, Deputy Chief of the Defence Staff for Financial and Military Capability, in evidence to the committee on 28 May.

AM Knighton confirmed the Ajax vehicles made by General Dynamics Land Systems-UK (GDLS-UK) were not ready to be accepted by the British Army as planned last year.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/29cf9003-fcc5-4c72-af61-e7a41a7aa603/

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) ...

UK to reassess Ajax programme

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) Ajax programme after the first batch of production standard armoured fighting vehicles (AFVs) was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

Details of the exercise are still being worked out and the MoD’s chief civilian administrator, Stephen Lovegrove, is preparing to issue a formal notification to the UK parliament’s Public Accounts Committee about the reassessment. These notifications are only made when major cost overruns, technical glitches or programme delays are involved.

The revelation of the reassessment was made by Air Marshal Richard Knighton, Deputy Chief of the Defence Staff for Financial and Military Capability, in evidence to the committee on 28 May.

AM Knighton confirmed the Ajax vehicles made by General Dynamics Land Systems-UK (GDLS-UK) were not ready to be accepted by the British Army as planned last year.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/29cf9003-fcc5-4c72-af61-e7a41a7aa603/

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) ...

UK to reassess Ajax programme

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) Ajax programme after the first batch of production standard armoured fighting vehicles (AFVs) was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

Details of the exercise are still being worked out and the MoD’s chief civilian administrator, Stephen Lovegrove, is preparing to issue a formal notification to the UK parliament’s Public Accounts Committee about the reassessment. These notifications are only made when major cost overruns, technical glitches or programme delays are involved.

The revelation of the reassessment was made by Air Marshal Richard Knighton, Deputy Chief of the Defence Staff for Financial and Military Capability, in evidence to the committee on 28 May.

AM Knighton confirmed the Ajax vehicles made by General Dynamics Land Systems-UK (GDLS-UK) were not ready to be accepted by the British Army as planned last year.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/29cf9003-fcc5-4c72-af61-e7a41a7aa603/

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) ...

UK to reassess Ajax programme

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) Ajax programme after the first batch of production standard armoured fighting vehicles (AFVs) was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

Details of the exercise are still being worked out and the MoD’s chief civilian administrator, Stephen Lovegrove, is preparing to issue a formal notification to the UK parliament’s Public Accounts Committee about the reassessment. These notifications are only made when major cost overruns, technical glitches or programme delays are involved.

The revelation of the reassessment was made by Air Marshal Richard Knighton, Deputy Chief of the Defence Staff for Financial and Military Capability, in evidence to the committee on 28 May.

AM Knighton confirmed the Ajax vehicles made by General Dynamics Land Systems-UK (GDLS-UK) were not ready to be accepted by the British Army as planned last year.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/29cf9003-fcc5-4c72-af61-e7a41a7aa603/

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) ...

UK to reassess Ajax programme

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) Ajax programme after the first batch of production standard armoured fighting vehicles (AFVs) was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

The UK MoD is reassessing the Ajax programme after the first batch of production standard AFVs was found not to be ready for delivery.

Details of the exercise are still being worked out and the MoD’s chief civilian administrator, Stephen Lovegrove, is preparing to issue a formal notification to the UK parliament’s Public Accounts Committee about the reassessment. These notifications are only made when major cost overruns, technical glitches or programme delays are involved.

The revelation of the reassessment was made by Air Marshal Richard Knighton, Deputy Chief of the Defence Staff for Financial and Military Capability, in evidence to the committee on 28 May.

AM Knighton confirmed the Ajax vehicles made by General Dynamics Land Systems-UK (GDLS-UK) were not ready to be accepted by the British Army as planned last year.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/29cf9003-fcc5-4c72-af61-e7a41a7aa603/

UK Ministry of Defence (MoD) procurement chiefs are reassessing the GBP5.3 billion (USD6.7 billion) ...