Fincantieri announces start of construction for Italian Navy's first Type 212 NFS submarine

by Kate Tringham

A graphic depiction of the Italian Navy's Type 212 NFS. Fincantieri has started construction on the first boat at its Muggiano shipyard in La Spezia. (Italian Navy)

Fincantieri launched the start of construction for the Italian Navy's first new Type 212 NFS (Near Future Submarine) at its Muggiano shipyard in La Spezia on 11 January.

Under the Type 212 NFS programme, the Italian Navy is planning to procure four new boats evolved from the service's existing Todaro (Type 212A)-class air-independent propulsion diesel-electric submarines (SSKs).

Fincantieri was awarded a contract worth EUR1.35 billion (USD1.63 billion) to build the first pair under a contract awarded via the Organisation for Joint Armament Co-operation (OCCAR) in February 2021. Under the agreement terms, the two submarines are expected to be delivered in 2027 and 2029.

The contract includes an option for the two follow-on submarines.


Get the full article by
Already a Janes subscriber? Keep reading


Construction for guided-missile frigate Constellation set to begin

by Michael Fabey

The US Navy recently exercised an option to acquire the guided-missile frigate Chesapeake (FFG 64). (US Navy)

Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-missile frigate (FFG 62) close to the scheduled construction-start time, programme sources confirmed.

FMM and US Navy (USN) sources say Constellation work will begin during the US summer – that started 21 June and ends 22 September – but a source familiar with the programme told Janes the shipbuilder will likely begin construction in August.

That start is a bit later than the US Government Accountability Office (GAO) had indicated in its annual report on major Pentagon acquisition programmes, released on 8 June.

“The [FFG 62] programme office confirmed that the programme delayed the start of lead ship construction planned for April 2022,” the GAO reported. “The official said that the programme now plans to begin construction in July 2022.”

Officially, though, FMM spokesperson Eric Dent told Janes, “We are planning to start construction of the lead ship, the future USS Constellation, this summer.”


Get the full article by
Already a Janes subscriber? Keep reading


Keel laid for first new Bulgarian MMPV

by Aleksandar Mladenov & Krasimir Grozev

The keel-laying ceremony for the first of two Multipurpose Modular Patrol Vessels to be built for the Bulgarian Navy was held on 17 June at MTG Dolphin's shipyard near Varna, in the attendance of country's president, Rumen Radev, and the minister of defence, Dragomir Zakov. (Bulgarian Navy)

German shipbuilder NVL Group (formerly Lürssen Werft) held a keel-laying ceremony for the first of two Multipurpose Modular Patrol Vessels (MMPVs) on order for the Bulgarian Navy at the yard of its local shipbuilding partner MTG Dolphin in Varna, Bulgaria on 17 June.

The new ship, named Hrabri (12), is planned to be delivered to the Bulgarian Navy in late 2025. Meanwhile, the keel for sister ship Smeli (11) will be laid in early 2023 and is expected to be handed over in late 2026.

The MMPVs are being built under a contract signed with NVL Group on 12 November 2020 valued at BGN820 million (USD473 million). The vessels are based on the NVL Group's OPV-90 model.


Get the full article by
Already a Janes subscriber? Keep reading


Indonesian shipyard begins work on new missile-capable ‘president ship'

by Ridzwan Rahmat

Indonesian private shipyard PT Karimun Anugrah Sejati (KAS) has begun work on a new guided-missile corvette that will double up as transport for dignitaries such as the Indonesian president.

A ceremony to mark the vessel's “first steel-cutting” and keel-laying was held on 9 June at PT KAS's shipbuilding facilities in Batam, Indonesia, a representative from the company has confirmed with Janes . It will be known as KRI Bung Karno once it is commissioned.

Actual work on the vessel's keel began in March 2022, but the “first steel-cutting” ceremony was held in conjunction with a visit by the Indonesian Navy's Logistics Assistant to the Chief of Naval Staff, Rear Admiral Puguh Santoso, to the facilities that day, the company said.

An IDR300 billion (USD20.2 million) contract to build the vessel was signed between PT KAS and the Indonesian defence in 2021. It has an overall length of about 73 m and will be powered by two MTU 16V 4000 M71 diesel engines that can propel the vessel to a top speed of 24 kt and a cruising speed of 16 kt.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/naval-weapons/latest/fincantieri-announces-start-of-construction-for-italian-navys-first-type-212-nfs-submarine

Fincantieri launched the start of construction for the Italian Navy's first new Type 212 NFS (Near F...

Latest Podcasts

Ukraine Conflict Review (April 2022)

Podcast recording date: 26 April 2022. Huw Williams of our EMEA news team chairs a discussion focussed on the Russian invasion of Ukraine featuring Amael Kotlarski, Senior Analyst at Janes, Thomas Bullock, Senior Russia and CIS OSINT Analyst a...

Listen now

Coming of Age for OSINT Technology: A Conversation with Emily Harding

The application of OSINT in the counter-terrorist role

Ukraine Conflict: A Review of the First Week

Russia/Ukraine - Coming of Age for OSINT?

Janes Case Studies

Using Janes Intara to build a common intelligence picture: Russian build up on the Ukrainian border

View Case Study

Assessing threats in the South China Sea 

A competitive assessment of the military aircraft market

Identifying an unknown aircraft

Case study: Using Interconnected Intelligence to Monitor Russian Troop Movement

News Categories

Request Consultation

Request a free consultation to discover how Janes can provide you with assured, interconnected open-source intelligence.

Sea Details