27 February 2023
by Akhil Kadidal
Australia's acquisition of three MQ-4C Triton HALE UAS is linked to the retirement of the RAAF's Lockheed AP-3C Orion fleet, which is scheduled to take place in 2023. (Northrop Grumman)
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Australia is being prepared for its first test flight in mid-2023.
The Australian Tritons are progressing to schedule, Northrop Grumman officials told Janes . “The flight of the first Australian Triton, ‘AUS1,' is expected to happen in the summer of 2023,” said Rho Cauley-Bruner, Triton programme manager.
“AUS1 is now in the test phase with the first flight scheduled to happen in [the third quarter] Q3 [of] this year. We anticipate delivery of that aircraft to Australia in mid-2024. [The] AUS2 wingmate occurred in January 2023 and that build is progressing to plan. AUS3 is in production in Moss Point, with a scheduled delivery to Palmdale, where it will be mated with its wing in April 2023,” Cauley-Bruner added.
Northrop Grumman is also working towards achieving initial operational capability (IOC) of its Integrated Functional Capability 4 (IFC-4) configuration being developed for the Triton programme.
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Aust...
27 February 2023
by Akhil Kadidal
Australia's acquisition of three MQ-4C Triton HALE UAS is linked to the retirement of the RAAF's Lockheed AP-3C Orion fleet, which is scheduled to take place in 2023. (Northrop Grumman)
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Australia is being prepared for its first test flight in mid-2023.
The Australian Tritons are progressing to schedule, Northrop Grumman officials told Janes . “The flight of the first Australian Triton, ‘AUS1,' is expected to happen in the summer of 2023,” said Rho Cauley-Bruner, Triton programme manager.
“AUS1 is now in the test phase with the first flight scheduled to happen in [the third quarter] Q3 [of] this year. We anticipate delivery of that aircraft to Australia in mid-2024. [The] AUS2 wingmate occurred in January 2023 and that build is progressing to plan. AUS3 is in production in Moss Point, with a scheduled delivery to Palmdale, where it will be mated with its wing in April 2023,” Cauley-Bruner added.
Northrop Grumman is also working towards achieving initial operational capability (IOC) of its Integrated Functional Capability 4 (IFC-4) configuration being developed for the Triton programme.
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Aust...
27 February 2023
by Akhil Kadidal
Australia's acquisition of three MQ-4C Triton HALE UAS is linked to the retirement of the RAAF's Lockheed AP-3C Orion fleet, which is scheduled to take place in 2023. (Northrop Grumman)
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Australia is being prepared for its first test flight in mid-2023.
The Australian Tritons are progressing to schedule, Northrop Grumman officials told Janes . “The flight of the first Australian Triton, ‘AUS1,' is expected to happen in the summer of 2023,” said Rho Cauley-Bruner, Triton programme manager.
“AUS1 is now in the test phase with the first flight scheduled to happen in [the third quarter] Q3 [of] this year. We anticipate delivery of that aircraft to Australia in mid-2024. [The] AUS2 wingmate occurred in January 2023 and that build is progressing to plan. AUS3 is in production in Moss Point, with a scheduled delivery to Palmdale, where it will be mated with its wing in April 2023,” Cauley-Bruner added.
Northrop Grumman is also working towards achieving initial operational capability (IOC) of its Integrated Functional Capability 4 (IFC-4) configuration being developed for the Triton programme.
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Aust...
27 February 2023
by Akhil Kadidal
Australia's acquisition of three MQ-4C Triton HALE UAS is linked to the retirement of the RAAF's Lockheed AP-3C Orion fleet, which is scheduled to take place in 2023. (Northrop Grumman)
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Australia is being prepared for its first test flight in mid-2023.
The Australian Tritons are progressing to schedule, Northrop Grumman officials told Janes . “The flight of the first Australian Triton, ‘AUS1,' is expected to happen in the summer of 2023,” said Rho Cauley-Bruner, Triton programme manager.
“AUS1 is now in the test phase with the first flight scheduled to happen in [the third quarter] Q3 [of] this year. We anticipate delivery of that aircraft to Australia in mid-2024. [The] AUS2 wingmate occurred in January 2023 and that build is progressing to plan. AUS3 is in production in Moss Point, with a scheduled delivery to Palmdale, where it will be mated with its wing in April 2023,” Cauley-Bruner added.
Northrop Grumman is also working towards achieving initial operational capability (IOC) of its Integrated Functional Capability 4 (IFC-4) configuration being developed for the Triton programme.
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Aust...
27 February 2023
by Akhil Kadidal
Australia's acquisition of three MQ-4C Triton HALE UAS is linked to the retirement of the RAAF's Lockheed AP-3C Orion fleet, which is scheduled to take place in 2023. (Northrop Grumman)
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Australia is being prepared for its first test flight in mid-2023.
The Australian Tritons are progressing to schedule, Northrop Grumman officials told Janes . “The flight of the first Australian Triton, ‘AUS1,' is expected to happen in the summer of 2023,” said Rho Cauley-Bruner, Triton programme manager.
“AUS1 is now in the test phase with the first flight scheduled to happen in [the third quarter] Q3 [of] this year. We anticipate delivery of that aircraft to Australia in mid-2024. [The] AUS2 wingmate occurred in January 2023 and that build is progressing to plan. AUS3 is in production in Moss Point, with a scheduled delivery to Palmdale, where it will be mated with its wing in April 2023,” Cauley-Bruner added.
Northrop Grumman is also working towards achieving initial operational capability (IOC) of its Integrated Functional Capability 4 (IFC-4) configuration being developed for the Triton programme.
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Aust...
27 February 2023
by Akhil Kadidal
Australia's acquisition of three MQ-4C Triton HALE UAS is linked to the retirement of the RAAF's Lockheed AP-3C Orion fleet, which is scheduled to take place in 2023. (Northrop Grumman)
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Australia is being prepared for its first test flight in mid-2023.
The Australian Tritons are progressing to schedule, Northrop Grumman officials told Janes . “The flight of the first Australian Triton, ‘AUS1,' is expected to happen in the summer of 2023,” said Rho Cauley-Bruner, Triton programme manager.
“AUS1 is now in the test phase with the first flight scheduled to happen in [the third quarter] Q3 [of] this year. We anticipate delivery of that aircraft to Australia in mid-2024. [The] AUS2 wingmate occurred in January 2023 and that build is progressing to plan. AUS3 is in production in Moss Point, with a scheduled delivery to Palmdale, where it will be mated with its wing in April 2023,” Cauley-Bruner added.
Northrop Grumman is also working towards achieving initial operational capability (IOC) of its Integrated Functional Capability 4 (IFC-4) configuration being developed for the Triton programme.
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Aust...
27 February 2023
by Akhil Kadidal
Australia's acquisition of three MQ-4C Triton HALE UAS is linked to the retirement of the RAAF's Lockheed AP-3C Orion fleet, which is scheduled to take place in 2023. (Northrop Grumman)
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Australia is being prepared for its first test flight in mid-2023.
The Australian Tritons are progressing to schedule, Northrop Grumman officials told Janes . “The flight of the first Australian Triton, ‘AUS1,' is expected to happen in the summer of 2023,” said Rho Cauley-Bruner, Triton programme manager.
“AUS1 is now in the test phase with the first flight scheduled to happen in [the third quarter] Q3 [of] this year. We anticipate delivery of that aircraft to Australia in mid-2024. [The] AUS2 wingmate occurred in January 2023 and that build is progressing to plan. AUS3 is in production in Moss Point, with a scheduled delivery to Palmdale, where it will be mated with its wing in April 2023,” Cauley-Bruner added.
Northrop Grumman is also working towards achieving initial operational capability (IOC) of its Integrated Functional Capability 4 (IFC-4) configuration being developed for the Triton programme.
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Aust...
27 February 2023
by Akhil Kadidal
Australia's acquisition of three MQ-4C Triton HALE UAS is linked to the retirement of the RAAF's Lockheed AP-3C Orion fleet, which is scheduled to take place in 2023. (Northrop Grumman)
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Australia is being prepared for its first test flight in mid-2023.
The Australian Tritons are progressing to schedule, Northrop Grumman officials told Janes . “The flight of the first Australian Triton, ‘AUS1,' is expected to happen in the summer of 2023,” said Rho Cauley-Bruner, Triton programme manager.
“AUS1 is now in the test phase with the first flight scheduled to happen in [the third quarter] Q3 [of] this year. We anticipate delivery of that aircraft to Australia in mid-2024. [The] AUS2 wingmate occurred in January 2023 and that build is progressing to plan. AUS3 is in production in Moss Point, with a scheduled delivery to Palmdale, where it will be mated with its wing in April 2023,” Cauley-Bruner added.
Northrop Grumman is also working towards achieving initial operational capability (IOC) of its Integrated Functional Capability 4 (IFC-4) configuration being developed for the Triton programme.
The first of the three Northrop Grumman MQ-4C Triton unmanned aerial vehicles (UAVs) ordered by Aust...