27 September 2022
by Tim Ripley
The UK MoD does not expect a delay in the Boxer programme, despite supply chain pressures. (Rheinmetall)
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicle programme, according to the UK Ministry of Defence (MoD).
The British Army's Boxer programme director, Colonel Iain Fake, said on the second day of the Defence Vehicle Dynamics (DVD) 2022 event held at the Millbrook Proving Ground from 21 to 22 September that some electronic components were taking 55 weeks to source because of the Covid-19 pandemic and the Ukraine war.
An MoD spokesperson told Janes on 26 September, “Production is successfully under way for Boxer and 623 of the new armoured vehicles will be delivered to the British Army. Global supply chain pressures are not unique to defence, and no delays are expected for the first deliveries in 2023 or Boxer's initial operational capability (IOC) in 2025.”
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicl...
27 September 2022
by Tim Ripley
The UK MoD does not expect a delay in the Boxer programme, despite supply chain pressures. (Rheinmetall)
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicle programme, according to the UK Ministry of Defence (MoD).
The British Army's Boxer programme director, Colonel Iain Fake, said on the second day of the Defence Vehicle Dynamics (DVD) 2022 event held at the Millbrook Proving Ground from 21 to 22 September that some electronic components were taking 55 weeks to source because of the Covid-19 pandemic and the Ukraine war.
An MoD spokesperson told Janes on 26 September, “Production is successfully under way for Boxer and 623 of the new armoured vehicles will be delivered to the British Army. Global supply chain pressures are not unique to defence, and no delays are expected for the first deliveries in 2023 or Boxer's initial operational capability (IOC) in 2025.”
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicl...
27 September 2022
by Tim Ripley
The UK MoD does not expect a delay in the Boxer programme, despite supply chain pressures. (Rheinmetall)
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicle programme, according to the UK Ministry of Defence (MoD).
The British Army's Boxer programme director, Colonel Iain Fake, said on the second day of the Defence Vehicle Dynamics (DVD) 2022 event held at the Millbrook Proving Ground from 21 to 22 September that some electronic components were taking 55 weeks to source because of the Covid-19 pandemic and the Ukraine war.
An MoD spokesperson told Janes on 26 September, “Production is successfully under way for Boxer and 623 of the new armoured vehicles will be delivered to the British Army. Global supply chain pressures are not unique to defence, and no delays are expected for the first deliveries in 2023 or Boxer's initial operational capability (IOC) in 2025.”
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicl...
27 September 2022
by Tim Ripley
The UK MoD does not expect a delay in the Boxer programme, despite supply chain pressures. (Rheinmetall)
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicle programme, according to the UK Ministry of Defence (MoD).
The British Army's Boxer programme director, Colonel Iain Fake, said on the second day of the Defence Vehicle Dynamics (DVD) 2022 event held at the Millbrook Proving Ground from 21 to 22 September that some electronic components were taking 55 weeks to source because of the Covid-19 pandemic and the Ukraine war.
An MoD spokesperson told Janes on 26 September, “Production is successfully under way for Boxer and 623 of the new armoured vehicles will be delivered to the British Army. Global supply chain pressures are not unique to defence, and no delays are expected for the first deliveries in 2023 or Boxer's initial operational capability (IOC) in 2025.”
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicl...
27 September 2022
by Tim Ripley
The UK MoD does not expect a delay in the Boxer programme, despite supply chain pressures. (Rheinmetall)
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicle programme, according to the UK Ministry of Defence (MoD).
The British Army's Boxer programme director, Colonel Iain Fake, said on the second day of the Defence Vehicle Dynamics (DVD) 2022 event held at the Millbrook Proving Ground from 21 to 22 September that some electronic components were taking 55 weeks to source because of the Covid-19 pandemic and the Ukraine war.
An MoD spokesperson told Janes on 26 September, “Production is successfully under way for Boxer and 623 of the new armoured vehicles will be delivered to the British Army. Global supply chain pressures are not unique to defence, and no delays are expected for the first deliveries in 2023 or Boxer's initial operational capability (IOC) in 2025.”
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicl...
27 September 2022
by Tim Ripley
The UK MoD does not expect a delay in the Boxer programme, despite supply chain pressures. (Rheinmetall)
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicle programme, according to the UK Ministry of Defence (MoD).
The British Army's Boxer programme director, Colonel Iain Fake, said on the second day of the Defence Vehicle Dynamics (DVD) 2022 event held at the Millbrook Proving Ground from 21 to 22 September that some electronic components were taking 55 weeks to source because of the Covid-19 pandemic and the Ukraine war.
An MoD spokesperson told Janes on 26 September, “Production is successfully under way for Boxer and 623 of the new armoured vehicles will be delivered to the British Army. Global supply chain pressures are not unique to defence, and no delays are expected for the first deliveries in 2023 or Boxer's initial operational capability (IOC) in 2025.”
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicl...
27 September 2022
by Tim Ripley
The UK MoD does not expect a delay in the Boxer programme, despite supply chain pressures. (Rheinmetall)
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicle programme, according to the UK Ministry of Defence (MoD).
The British Army's Boxer programme director, Colonel Iain Fake, said on the second day of the Defence Vehicle Dynamics (DVD) 2022 event held at the Millbrook Proving Ground from 21 to 22 September that some electronic components were taking 55 weeks to source because of the Covid-19 pandemic and the Ukraine war.
An MoD spokesperson told Janes on 26 September, “Production is successfully under way for Boxer and 623 of the new armoured vehicles will be delivered to the British Army. Global supply chain pressures are not unique to defence, and no delays are expected for the first deliveries in 2023 or Boxer's initial operational capability (IOC) in 2025.”
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicl...
27 September 2022
by Tim Ripley
The UK MoD does not expect a delay in the Boxer programme, despite supply chain pressures. (Rheinmetall)
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicle programme, according to the UK Ministry of Defence (MoD).
The British Army's Boxer programme director, Colonel Iain Fake, said on the second day of the Defence Vehicle Dynamics (DVD) 2022 event held at the Millbrook Proving Ground from 21 to 22 September that some electronic components were taking 55 weeks to source because of the Covid-19 pandemic and the Ukraine war.
An MoD spokesperson told Janes on 26 September, “Production is successfully under way for Boxer and 623 of the new armoured vehicles will be delivered to the British Army. Global supply chain pressures are not unique to defence, and no delays are expected for the first deliveries in 2023 or Boxer's initial operational capability (IOC) in 2025.”
Supply chain pressures are not expected to delay the British Army's Boxer Mechanised Infantry Vehicl...