23 June 2022
by Michael Fabey
The US Navy recently exercised an option to acquire the guided-missile frigate Chesapeake (FFG 64). (US Navy)
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-missile frigate (FFG 62) close to the scheduled construction-start time, programme sources confirmed.
FMM and US Navy (USN) sources say Constellation work will begin during the US summer – that started 21 June and ends 22 September – but a source familiar with the programme told Janes the shipbuilder will likely begin construction in August.
That start is a bit later than the US Government Accountability Office (GAO) had indicated in its annual report on major Pentagon acquisition programmes, released on 8 June.
“The [FFG 62] programme office confirmed that the programme delayed the start of lead ship construction planned for April 2022,” the GAO reported. “The official said that the programme now plans to begin construction in July 2022.”
Officially, though, FMM spokesperson Eric Dent told Janes, “We are planning to start construction of the lead ship, the future USS Constellation, this summer.”
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-mis...
23 June 2022
by Michael Fabey
The US Navy recently exercised an option to acquire the guided-missile frigate Chesapeake (FFG 64). (US Navy)
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-missile frigate (FFG 62) close to the scheduled construction-start time, programme sources confirmed.
FMM and US Navy (USN) sources say Constellation work will begin during the US summer – that started 21 June and ends 22 September – but a source familiar with the programme told Janes the shipbuilder will likely begin construction in August.
That start is a bit later than the US Government Accountability Office (GAO) had indicated in its annual report on major Pentagon acquisition programmes, released on 8 June.
“The [FFG 62] programme office confirmed that the programme delayed the start of lead ship construction planned for April 2022,” the GAO reported. “The official said that the programme now plans to begin construction in July 2022.”
Officially, though, FMM spokesperson Eric Dent told Janes, “We are planning to start construction of the lead ship, the future USS Constellation, this summer.”
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-mis...
23 June 2022
by Michael Fabey
The US Navy recently exercised an option to acquire the guided-missile frigate Chesapeake (FFG 64). (US Navy)
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-missile frigate (FFG 62) close to the scheduled construction-start time, programme sources confirmed.
FMM and US Navy (USN) sources say Constellation work will begin during the US summer – that started 21 June and ends 22 September – but a source familiar with the programme told Janes the shipbuilder will likely begin construction in August.
That start is a bit later than the US Government Accountability Office (GAO) had indicated in its annual report on major Pentagon acquisition programmes, released on 8 June.
“The [FFG 62] programme office confirmed that the programme delayed the start of lead ship construction planned for April 2022,” the GAO reported. “The official said that the programme now plans to begin construction in July 2022.”
Officially, though, FMM spokesperson Eric Dent told Janes, “We are planning to start construction of the lead ship, the future USS Constellation, this summer.”
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-mis...
23 June 2022
by Michael Fabey
The US Navy recently exercised an option to acquire the guided-missile frigate Chesapeake (FFG 64). (US Navy)
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-missile frigate (FFG 62) close to the scheduled construction-start time, programme sources confirmed.
FMM and US Navy (USN) sources say Constellation work will begin during the US summer – that started 21 June and ends 22 September – but a source familiar with the programme told Janes the shipbuilder will likely begin construction in August.
That start is a bit later than the US Government Accountability Office (GAO) had indicated in its annual report on major Pentagon acquisition programmes, released on 8 June.
“The [FFG 62] programme office confirmed that the programme delayed the start of lead ship construction planned for April 2022,” the GAO reported. “The official said that the programme now plans to begin construction in July 2022.”
Officially, though, FMM spokesperson Eric Dent told Janes, “We are planning to start construction of the lead ship, the future USS Constellation, this summer.”
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-mis...
23 June 2022
by Michael Fabey
The US Navy recently exercised an option to acquire the guided-missile frigate Chesapeake (FFG 64). (US Navy)
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-missile frigate (FFG 62) close to the scheduled construction-start time, programme sources confirmed.
FMM and US Navy (USN) sources say Constellation work will begin during the US summer – that started 21 June and ends 22 September – but a source familiar with the programme told Janes the shipbuilder will likely begin construction in August.
That start is a bit later than the US Government Accountability Office (GAO) had indicated in its annual report on major Pentagon acquisition programmes, released on 8 June.
“The [FFG 62] programme office confirmed that the programme delayed the start of lead ship construction planned for April 2022,” the GAO reported. “The official said that the programme now plans to begin construction in July 2022.”
Officially, though, FMM spokesperson Eric Dent told Janes, “We are planning to start construction of the lead ship, the future USS Constellation, this summer.”
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-mis...
23 June 2022
by Michael Fabey
The US Navy recently exercised an option to acquire the guided-missile frigate Chesapeake (FFG 64). (US Navy)
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-missile frigate (FFG 62) close to the scheduled construction-start time, programme sources confirmed.
FMM and US Navy (USN) sources say Constellation work will begin during the US summer – that started 21 June and ends 22 September – but a source familiar with the programme told Janes the shipbuilder will likely begin construction in August.
That start is a bit later than the US Government Accountability Office (GAO) had indicated in its annual report on major Pentagon acquisition programmes, released on 8 June.
“The [FFG 62] programme office confirmed that the programme delayed the start of lead ship construction planned for April 2022,” the GAO reported. “The official said that the programme now plans to begin construction in July 2022.”
Officially, though, FMM spokesperson Eric Dent told Janes, “We are planning to start construction of the lead ship, the future USS Constellation, this summer.”
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-mis...
23 June 2022
by Michael Fabey
The US Navy recently exercised an option to acquire the guided-missile frigate Chesapeake (FFG 64). (US Navy)
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-missile frigate (FFG 62) close to the scheduled construction-start time, programme sources confirmed.
FMM and US Navy (USN) sources say Constellation work will begin during the US summer – that started 21 June and ends 22 September – but a source familiar with the programme told Janes the shipbuilder will likely begin construction in August.
That start is a bit later than the US Government Accountability Office (GAO) had indicated in its annual report on major Pentagon acquisition programmes, released on 8 June.
“The [FFG 62] programme office confirmed that the programme delayed the start of lead ship construction planned for April 2022,” the GAO reported. “The official said that the programme now plans to begin construction in July 2022.”
Officially, though, FMM spokesperson Eric Dent told Janes, “We are planning to start construction of the lead ship, the future USS Constellation, this summer.”
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-mis...
23 June 2022
by Michael Fabey
The US Navy recently exercised an option to acquire the guided-missile frigate Chesapeake (FFG 64). (US Navy)
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-missile frigate (FFG 62) close to the scheduled construction-start time, programme sources confirmed.
FMM and US Navy (USN) sources say Constellation work will begin during the US summer – that started 21 June and ends 22 September – but a source familiar with the programme told Janes the shipbuilder will likely begin construction in August.
That start is a bit later than the US Government Accountability Office (GAO) had indicated in its annual report on major Pentagon acquisition programmes, released on 8 June.
“The [FFG 62] programme office confirmed that the programme delayed the start of lead ship construction planned for April 2022,” the GAO reported. “The official said that the programme now plans to begin construction in July 2022.”
Officially, though, FMM spokesperson Eric Dent told Janes, “We are planning to start construction of the lead ship, the future USS Constellation, this summer.”
Fincantieri Marinette Marine (FMM) is set to start building the first Constellation-class guided-mis...